Latest news and updates

Key dates


 Contract award   December 2017
 Start of construction   Monday 5th March 2018
 All buses shift to TCR   Early 2019
 End of construction   Early 2020

You can now download the two year programme for Tottenham Court Road and Gower Street. We are working in phases across the area to minimise disruption. Listed below are the details for the first phase. This page will continue to be updated with the latest phasing information. For the weekly look ahead click here.

Phase 1 works:

University Street – Queen’s Yard                               4th June – end of June
Queens Yard - Torrington Place                                26th June – end of July

Alfred Mews - Chenies Street                                     4th June – end of June
Chenies Street - Store Street                                     19th June – end of July

Bedford Avenue - Great Russell Street                      4th June – end of June
Great Russell Square - New Oxford Street                13th June – mid July

 You can also sign up to the West End Project newsletter.

Would you like to provide feedback?(Click to show feedback form)

Please rate this page to help us improve camden.gov.uk. Please don't include your contact details as we are unable to provide responses via this form. To get in touch please click here.

Please select one of the options.

Thank you for your feedback.